Time and materials contract

A time and materials (T&M) contract pays the contractor for labor hours at agreed hourly rates, which already include overhead and profit, plus the cost of materials, sometimes with a markup.

Updated November 9, 2026 · 1 min read

On this page
  1. When it fits
  2. What protects both sides
  3. An example

When it fits

Repairs and service work where nobody knows the scope until the wall is open: a leak with no obvious source, an old panel that may need rewiring, storm damage. Federal rules capture the idea well. FAR 16.601 allows T&M only when the extent or duration of the work can't be estimated accurately up front, and requires a ceiling price the contractor exceeds at its own risk.

What protects both sides

  • A not-to-exceed amount the contractor can't pass without written approval.
  • The hourly rate for each kind of worker, and any overtime or emergency rate.
  • How materials are billed: at cost, or at cost plus a stated markup.
  • Daily time records and receipts the customer can see.

An example

A homeowner's ceiling is stained but the roof looks fine. The roofer agrees an hourly rate, materials at cost plus a set percent, and a not-to-exceed figure. The leak turns out to be a cracked boot on a vent pipe, so the bill comes in well under the cap.

SignMaster's roof repair agreement and plumbing service agreement templates both offer a time and materials option with an hourly rate and a not-to-exceed amount the contractor won't pass without the customer's written approval.

Sources

  1. Federal Acquisition Regulation 16.601, time-and-materials contracts · acquisition.gov