A notice of completion is a document the property owner records with the county to state that a construction project is finished. In the states that use it, recording one shortens the time contractors, subcontractors and suppliers have to record a mechanics lien.

Updated November 9, 2026 · 1 min read

On this page
  1. Why it matters
  2. Two states, as examples
  3. An example
  4. Questions

Why it matters

For owners, it closes the lien window sooner. For anyone still owed money, it's a countdown: once it's recorded, the clock may run in weeks, not months.

Two states, as examples

  • California (Civil Code §§ 8182, 8412, 8414): the owner may record it within 15 days after completion, signed and verified. The direct contractor then has 60 days from recording to record a lien, and everyone else 30, instead of 90 days from completion. Unless an exception applies, such as an owner living in a home of four units or fewer, the owner must send a copy within 10 days to the direct contractor and anyone who gave a preliminary notice, or it doesn't shorten that person's deadline.
  • Arizona (A.R.S. § 33-993): a lien must be recorded within 120 days after completion, or within 60 days after a notice of completion is recorded.

An example

A California remodel is finished on May 28 and the owner records a notice of completion on June 2. A tile sub who served a preliminary notice and is still owed now has until July 2 to record a lien, not late August.

It isn't the same as the customer's sign-off. A job completion sign-off, which you can send in SignMaster, records that the customer accepted the work; the notice of completion is a county filing the owner makes.

General information, not legal advice

Completion has a legal definition in each state. Confirm your deadline in the statute or with a construction attorney.

Questions? Answers.

Does the owner have to record a notice of completion?

Not in California: the statute says an owner may record one. If none is recorded, the longer deadlines measured from completion apply.

Sources

  1. California Civil Code § 8182, notice of completion · leginfo.legislature.ca.gov
  2. California Civil Code § 8412, lien deadline for a direct contractor · leginfo.legislature.ca.gov
  3. California Civil Code § 8414, lien deadline for other claimants · leginfo.legislature.ca.gov
  4. California Civil Code § 8190, copies of a notice of completion · leginfo.legislature.ca.gov
  5. Arizona Revised Statutes § 33-993, deadline to record a lien · azleg.gov